Capacity Expansion of Continuous Centrifuge Station
As part of a planned capacity expansion of the existing continuous centrifuge station, three additional centrifuges were supplied.
The new PLL-3300-OTV centrifuges, jointly produced by PAF and OTAVA, were installed alongside the existing BMA K2300 centrifuges, increasing the overall capacity of the station.
Delivery of all three centrifuges was completed in May 2026. Installation supervision and commissioning were carried out by OTAVA LLC engineers, ensuring that the expanded centrifuge station was fully operational in time for the 2026/2027 sugar processing campaign.